All newsTwo planned outages Neah Bay/Sekiu/Clallam Bay (8/16), and then Sekiu/Clallam Bay (8/30)
Two scheduled power outages will affect electric service in the west end as follows:
Neah Bay/Sekiu/Clallam Bay
Friday, August 16 beginning at 12:01 am, and lasting until approximately 6:00 am.
This outage is required to replace transmission and distribution poles in Sekiu and Neah Bay. Automated phone calls will begin going out to those affected during the week prior.
Sekiu/Clallam Bay
Friday, August 30 beginning at 12:01 am, and lasting until approximately 6:00 am.
This outage is required to complete maintenance on the Sekiu Substation. Automated phone calls will begin going out to those affected during the week prior.
If you have any questions, please contact:
360-452-9771 or 1.800.542.7859.